The Urban Unit

Construction of STD Facility Sahiwal Fabrication, Supply, Installation & Commissioning of Mechanical, Electrical, Civil and Mics Works

Client:

The Urban Unit

Contract Duration / Year:

2018

Project Location:

Sahiwal

Discipline:

Mechanical, Electrical, Civil & Instrumentation

Project Status:

In Hand

Power Construction Corporation of China, Haveli Bahadur Shah

Construction of Mechanical Draft Cooling Tower & Water Treatment Building Concrete Foundation (1230MW CCPP Haveli Bahadur Shah).

Client:

Power Construction Corporation of China, Haveli Bahadur Shah

Contract Duration / Year:

2016

Project Location:

Haveli Bahadur Shah

Discipline:

Civil & Mechanical

Project Status:

Completed

Pak-American Fertilizer Ltd., Iskandarabad

Underground Piping Dia 24” from Banian Tree Area to Plant Site.

Client:

Pak-American Fertilizer Ltd., Iskandarabad

Contract Duration / Year:

1997-98

Project Location:

Iskandarabad

Discipline:

Mechanical & Civil

Project Status:

Completed

Pakistan Petroleum Ltd., Karachi

Installation, Erection, Comm. and Utilities i.e. Pipes, Fittings, Equipment. (MDEA Plant)

Client:

Pakistan Petroleum Ltd., Karachi

Contract Duration / Year:

2000-01

Project Location:

Shikarpur

Discipline:

Mechanical, Electrical Instrumentation & Civil

Project Status:

Completed

Pakistan Petroleum Ltd., Karachi

Construction of High and Low Pressure Oil and Gas Lines for Installation of Early Production Facility (EPF) for Adhi Well 13 at Adhi LPG / NGL Plant.

Client:

Pakistan Petroleum Ltd., Karachi

Contract Duration / Year:

2002

Project Location:

Adhi Field, Rawalpindi

Discipline:

Mechanical & Civil

Project Status:

Completed

Pakistan Petroleum Ltd., Karachi

Construction / Welding / Installation of 6 Inch Diameter Buried Feeder Line and Well Head / Surface Fittings for Adhi Well-15 Near Daultala Town, District Rawalpindi.

Client:

Pakistan Petroleum Ltd., Karachi

Contract Duration / Year:

2004

Project Location:

Adhi Field, Rawalpindi

Discipline:

Mechanical & Civil

Project Status:

Completed

WAPDA, T&G Division, GSC, NTDC, Lahore

Construction of Capacitors Base Foundations at 132 Kv Grid Station Shadman & Chunian

Client:

WAPDA, T&G Division, GSC, NTDC, Lahore

Contract Duration / Year:

2004

Project Location:

Lahore & Chunian

Discipline:

Civil

Project Status:

Completed

M/s. WAPDA TLC Division, NTDC, Lahore

Construction of Foundations For Electrical Equipment for 66 TransFirmer Bay and Extension of 11 KV Switch Room TransFirmer Way Switch Yard Fencing and Switch Yard Fencing At 66 KV Grid Station EMCO.

Client:

M/s. WAPDA TLC Division, NTDC, Lahore

Contract Duration / Year:

2004

Project Location:

Lahore

Discipline:

Civil

Project Status:

Completed

WAPDA, T&G Division, GSC, NTDC, Lahore

Construction of Capacitors Base Foundations at 132 KV Grid Station.

Client:

WAPDA, T&G Division, GSC, NTDC, Lahore

Contract Duration / Year:

2004

Project Location:

Lahore

Discipline:

Civil

Project Status:

Completed